Slope stabilization · Field execution

Ituango Hydroelectric Project · K0+900 slope deep drains

Drilling and installation of approximately 3,400 linear meters of 51 mm horizontal drains to stabilize the replacement road slope.

Corporate experience
≈3,400 m
Ø 51 mm horizontal drains executed
60–100 m
Length per drain
+70 %
Increase over the initial 2,000 m
Client
ESTYMA Estudios y Manejos S.A. · EPM project
Location
Ituango, Antioquia · Colombia
Period
Feb. 2024 – Mar. 2025
Type of work
Slope stabilization · Field execution
Status
Completed and closed out
Type of experience
Contract executed by GEOTECNIA & TÚNELES S.A.S.

Technical scope

Drilling and installation of deep horizontal drains to stabilize the K0+900 slope of the replacement road, left bank of the project.

Works executed directly by the firm at the face, with a crew and a drill operator with certified experience, measured and paid per linear meter against the owner’s supervisor. The initial scope of 2,000 m was extended during execution and the contract was closed out.

Main geotechnical challenges
  • 01Long drains (60 to 100 m) in the slope of a road in operation
Solutions implemented
  • 01Sub-horizontal drilling and installation of Ø 51 mm drainage pipe
  • 02Quantity control per linear meter with the owner’s supervisor
Gallery
Drilling platform on the slope, with the reservoir in the background
Drilling platform on the slope, with the reservoir in the background
Drilling crew on the slope
Drilling crew on the slope
Drain-drilling rig on the slope
Drain-drilling rig on the slope
Canyon and reservoir in the project area
Canyon and reservoir in the project area
Services applied
Let’s talk about your project

Let’s build solutions for your next project

Every project presents its own challenges. Our goal is to understand your needs and develop sound technical and construction alternatives.